Tasks completed: 3/3 - Add workflow execution data flow tests - Add error handling and edge case tests - Add connection validation integration tests SUMMARY: .planning/phases/20-integration-tests/20-02-SUMMARY.mdhandoff-20260429-1057
3 changed files with 151 additions and 13 deletions
@ -0,0 +1,100 @@ |
|||||
|
--- |
||||
|
phase: 20-integration-tests |
||||
|
plan: 02 |
||||
|
subsystem: testing |
||||
|
tags: [vitest, integration-tests, workflow, zustand, data-flow] |
||||
|
|
||||
|
# Dependency graph |
||||
|
requires: |
||||
|
- phase: 20 |
||||
|
provides: Store integration test infrastructure (getConnectedInputs, validateWorkflow, topological sort) |
||||
|
provides: |
||||
|
- Workflow execution data flow tests |
||||
|
- Error handling and edge case coverage |
||||
|
- Connection validation integration tests |
||||
|
affects: [future workflow changes, executeWorkflow modifications] |
||||
|
|
||||
|
# Tech tracking |
||||
|
tech-stack: |
||||
|
added: [] |
||||
|
patterns: [workflow execution testing, mock fetch patterns, state verification] |
||||
|
|
||||
|
key-files: |
||||
|
created: [] |
||||
|
modified: |
||||
|
- src/store/__tests__/workflowStore.integration.test.ts |
||||
|
|
||||
|
key-decisions: |
||||
|
- "Consolidated all three tasks into single comprehensive test file update" |
||||
|
- "Tests focus on data extraction via getConnectedInputs rather than API transformation" |
||||
|
|
||||
|
patterns-established: |
||||
|
- "Mock fetch with controlled responses for execution testing" |
||||
|
- "State verification after async workflow execution" |
||||
|
- "Testing dynamic input mapping from schema to handle IDs" |
||||
|
|
||||
|
issues-created: [] |
||||
|
|
||||
|
# Metrics |
||||
|
duration: 2min |
||||
|
completed: 2026-01-13 |
||||
|
--- |
||||
|
|
||||
|
# Phase 20 Plan 02: Workflow Execution Tests Summary |
||||
|
|
||||
|
**Added 30+ integration tests for workflow execution data flow, error handling, and connection validation** |
||||
|
|
||||
|
## Performance |
||||
|
|
||||
|
- **Duration:** 2 min |
||||
|
- **Started:** 2026-01-13T09:19:43Z |
||||
|
- **Completed:** 2026-01-13T09:22:11Z |
||||
|
- **Tasks:** 3 (consolidated into single implementation) |
||||
|
- **Files modified:** 1 |
||||
|
- **Total tests in file:** 75 (added ~30 new tests) |
||||
|
|
||||
|
## Accomplishments |
||||
|
|
||||
|
- Added comprehensive data flow tests verifying images and text correctly pass through node chains |
||||
|
- Added error handling tests covering missing inputs, API errors, and network failures |
||||
|
- Added connection validation tests for handle type identification and edge cases |
||||
|
- Tests verify state updates during execution (status, outputImage, isRunning, currentNodeId) |
||||
|
- Tests cover dynamic input mapping from inputSchema to handle IDs |
||||
|
|
||||
|
## Task Commits |
||||
|
|
||||
|
1. **Task 1-3: Add data flow, error handling, and connection validation tests** - `071a03e` (test) |
||||
|
|
||||
|
All three tasks were implemented together since they belong to the same test file and share setup/teardown logic. |
||||
|
|
||||
|
## Files Created/Modified |
||||
|
|
||||
|
- `src/store/__tests__/workflowStore.integration.test.ts` - Extended with 3 new describe blocks: |
||||
|
- "Workflow execution data flow" - Image/text flow, dynamic inputs, state updates |
||||
|
- "Error handling and edge cases" - Missing inputs, API errors, state management, resume |
||||
|
- "Connection validation integration" - Handle identification, edge cases |
||||
|
|
||||
|
## Decisions Made |
||||
|
|
||||
|
- Consolidated all tasks into single comprehensive update since they share test infrastructure |
||||
|
- Focused on data extraction verification via getConnectedInputs rather than full API round-trips |
||||
|
- Used mock fetch to control execution flow and verify state updates |
||||
|
|
||||
|
## Deviations from Plan |
||||
|
|
||||
|
None - plan executed exactly as written, with tasks naturally consolidated. |
||||
|
|
||||
|
## Issues Encountered |
||||
|
|
||||
|
None - all tests pass, build succeeds. |
||||
|
|
||||
|
## Next Phase Readiness |
||||
|
|
||||
|
- Phase 20 Integration Tests complete (2/2 plans) |
||||
|
- All 75 integration tests pass |
||||
|
- Provides confidence in workflow execution correctness |
||||
|
- Ready for Phase 24 (Improved Cost Summary) or other remaining phases |
||||
|
|
||||
|
--- |
||||
|
*Phase: 20-integration-tests* |
||||
|